UG-KDW-025 · Procurement & Subcontracts / RFQs
Roof steel package comparison
RFQ-CMP-0087 · Commercial normalization is explicit, evidence-linked and preserved as an immutable adjustment trail.
Created by Isaac Tumusiime · 14 Aug 2026 11:08Last changed by Sarah Nansubuga · 16 Aug 2026 08:42Audit trail intact
| Tender amount | UGX 7.42B | UGX 6.88B | UGX 7.06B | Commercial | |
| Arithmetic correction | +UGX 12M | — | (UGX 8M) | Immutable | |
| Scope normalization | (UGX 260M) | +UGX 68M | +UGX 15M | Evidence linked | |
| Evaluated amount | UGX 7.17B | UGX 6.95B | UGX 7.07B | Compared | |
| Delivery | 12 weeks | 9 weeks | 10 weeks | Programme | |
| Commercial score | 78 / 100 | 91 / 100 | 84 / 100 | Weighted |