UG-KDW-025 · Procurement & Subcontracts / Requisitions
Requisitions
Demand enters procurement with a package, need date, budget context and accountable approval path.
Open18
Awaiting approval6
At RFQ7
Above budget2
| REQ-0318 | Roof steel package | C.401 | Isaac Tumusiime | 28 Aug | UGX 6.61B | UGX 6.94B | Commercial director | Comparison ready | |
| REQ-0315 | Electrical containment | E.211 | Angela Auma | 05 Sep | UGX 812M | UGX 764M | Procurement manager | RFQ live | |
| REQ-0307 | Level 2 masonry | D.104 | Peter Okwera | 22 Aug | UGX 296M | UGX 281M | Project manager | Approved | |
| REQ-0298 | Generator servicing | P.044 | Samuel Kato | 17 Aug | UGX 42M | UGX 48M | Plant manager | Attention |